Execution Plan

Execution Roadmap

A phase board for moving from evidence synthesis to bench validation, integrated economics, site pilot design, and scale-up decision.

01

0-60 days

Evidence hardening

Turn literature-backed claims into a ranked validation register.

Deliverables
  • Claim register
  • Source quality score
  • Baseline AD comparison
  • Open measurement list
Exit criteriaEvery external claim maps to a source, a confidence level, and a next validation action.
Open related page
02

2-4 months

Bench validation

Measure feed variability, HTL conversion, and initial product quality under controlled conditions.

Deliverables
  • Feedstock assay
  • HTL mass balance
  • Biocrude composition
  • Aqueous phase screen
Exit criteriaMass balance closes and the base case remains plausible under measured sludge composition.
Open related page
03

3-5 months

Integrated scenario model

Connect HTL, anaerobic digestion, hydrotreating, aqueous phase treatment, and carbon intensity in one ledger.

Deliverables
  • Hybrid scenario model
  • Economic sensitivity table
  • Carbon intensity range
  • Risk distribution
Exit criteriaLow, base, and favorable scenarios produce transparent go/no-go signals.
Open related page
04

5-9 months

Site pilot package

Prepare a wastewater-site pilot that tests equipment, sidestreams, permitting, and operations together.

Deliverables
  • Pilot protocol
  • Sampling plan
  • Permit boundary
  • Operations dashboard
Exit criteriaThe host site can run a field demonstration without hiding treatment burden or safety risk.
Open related page
05

9-12 months

Scale-up decision

Decide whether to stop, revise, or fund a larger field demonstration.

Deliverables
  • Independent data review
  • Capex class estimate
  • Partner thesis
  • Demonstration gate memo
Exit criteriaThe integrated case beats the AD reference case on a defensible facility and carbon basis.
Open related page

Operating cadence

Weekly

Update claim register, model assumptions, risk log, and bench-test blockers.

Monthly

Refresh scenario economics, carbon intensity ranges, and partner-readiness notes.

Gate review

Advance only when evidence, economics, plant integration, and safety criteria all clear the phase gate.